Sample Example Builders workspace for demonstration only. Amounts, statuses, documents, and any signature UI on this page are fictional. They are not a legal instrument and have no contractual effect. Back to the Marsh Point financials tab

Potential Change Order Log

PCO Log

Tenant Improvement · Example City, NC

Original$4,850,000Prime contract
Approved changes+$31,1502 change orders
Revised contract$4,881,150As of this issue
Pending+$62,6004 in approval
PCO #TitleAmountStatusSubmittedRelated
PCO-001
Existing condition: unforeseen slab depression
Level the Suite 900 slab at the west core before setting millwork.
+$18,400ApprovedJun 27, 2026RFI-009
PCO-004
Owner-requested extra data drops
Six additional CAT6 drops at reception and the huddle room.
+$12,750ApprovedJul 20, 2026ASI-008
PCO-008
Scope add: second fume-hood bank
Owner added a second hood bank at the west lab. Pricing returned.
+$18,400Pending approvalAug 9, 2026
PCO-011
Alternate millwork species (pricing only)
White oak to walnut at reception. Withdrawn after the sample review.
+$6,100Void
PCO-012
Void: duplicate of ASI already in contract
Duplicate pricing of ASI-011 storefront. Do not bill.
+$3,200VoidASI-011
PCO-014
Mullion trim finish change
Dark bronze to champagne on storefront trim. Long-lead.
+$12,350Pending approvalAug 14, 2026ASI-014
PCO-021
Mullion / storefront ASI
Storefront ASI for the mullion / glazing package. Signatures on file.
+$18,000Pending approvalAug 17, 2026RFI-028
PCO-022
Storefront ASI: landing stills
Glazing mock-up stills and landing clips. Draft, no Sage PDF yet.
+$27,500DraftASI-016
PCO-023
AV electrical: Conf A and B
Dedicated circuits, backboxes, tray, floor boxes per ASI-016 / RFI-041.
+$13,850Pending approvalAug 19, 2026ASI-016 · RFI-041
Approved
+$31,150
Pending*
+$62,600
Log total†
$121,250
Powered by StructionWiseConfidential, project use · Landscape letter*Pending = Pending approval + Awaiting PM approval · †Excludes Void